With the September 1 deadline for the start of schools now approaching, school custodians and others are working seven-day weeks to finish repairing the damage done by flooding on July 22 and prepare schools for classes as usual.
"You should have seen this just a few weeks ago," the district's business manager, Shawn Yde, said in guiding a visitor around the lower level of the high school amidst the work on Sunday. The level was damaged by water that poured in through window wells during the record downpour.
Read the rest of this post on the blog

Nearly completed masonry, Richards School cafeteria
On Nov. 3, 2009, the voters of Whitefish Bay approved two bond referendum questions that authorized $22.6 million in maintenance and improvement work on five district schools. Following the vote, the Yes Yes Progress Committee, composed of area citizens, was formed to monitor the post election implementation of this work and provide updates about the progress.
Preliminary plans developed by the school district's Facilities Study Committee have been the centerpiece of improvement preparation until now. Those recommendations will be revisited in discussions over the coming months as the final details are set. Information about that process will be available on this website up until the start of construction.

View by individual school
Cumberland | Richards | Middle School | High School | Lydell
Estimated Project Costs
$22.6 million*
Construction Bid Amount
Due July 2010
Borrowed Funds
Anticipated: $22.6 million
Actual: $20 million**
Bond Interest Rate
Projected: 5.5%
Actual: 1.91%**
Additional Tax Levy
Projected: .71 mill rate #
Revised: .50 per thousand
* Maximum amount
authorized by the
referendum.
**Estimate on June 8
# $250 a year increase on a
home assessed at $350,000
(includes state aid reduction)
Architects
Bray Associates Architects Inc.
Madison, Milwaukee
Sheboygan
www.brayarch.com
414-226-0200
Construction Manager
C. D. Smith Construction
Fond du Lac
cd-smith.com
920-924-2900
School District
Whitefish Bay Schools
1200 E Fairmount Ave.
www.wfbschools.com
414-963-3922
Buildings: $117.4 million
Enrollment: 2,960
Key Dates
Construction Bidding
June 2010
Issuance of Bonds
January-June 2010
Ground Breaking
June 17, 2010
Construction Completion
August 2011
All dates are subject to change